Work Continues at the Municipal Complex. Asphalt Binder Paving and Main Power Transformer Installation! New Drone Video!

 

New Drone Video from Wayne Garriepy!

Looking South – Overview of the Site

Grading and Prepping for Site Paving

Binder Course Asphalt Paving Begins at the DPW Complex

Paving and Compaction

Contractors Working with Asphalt Paver

Vibratory Oscillating Roller Compacting Asphalt

Equipment Bays Rear of the Building

Birdseye View of West Entrance Paving

Binder Course Asphalt Complete

Windows Installed in Garage Area, Overhead Door Installation

Curbing Installation Begins

Admin Office Areas Windows Installed, Ready for Insulation

Insulation Installation in Admin Area

Masonry Work in Garage Area Nears Completion

Prepping for Concrete Apron at Garage Vehicle Entrances, Bollards Installed, Siding Continues

Concrete Apron Around the Building Complete

Prepping for Concrete Slab on Mezzanine Deck

Concrete Slab Installed on Mezzanine, Metal Stud Framing Underway

Stairs to Mezzanine in Garage Area

Windows Installed in Admin Area, Exterior Masonry & Siding

Front Admin Area Windows Installed, Siding & Masonry Complete

Long View to the Building

New DPW Main Power Transformer