Construction Progress

CLICK THE LINKS TO SEE PHOTOS OF MONTHLY PROGRESS

May 2018 Phase II Public Safety Building Footprint Expands as Excavation, Concrete/Forms, and Masonry Work Progresses

April 2018 Phase II Work Continues with Public Safety Building Site Work and Concrete Forms/Footings/Walls

March 2018 Demolition of the Old Highway Garage Complete and Phase II for Public Safety in Full Swing!

February 2018 New DPW Fully Operational!  Phase II Site Work for Police/Fire Building Underway!

January 2018 Phase I Substantial Completion Milestone!

December 2017 DPW Building Nearing Substantial Completion!  New Drone Video

November 2017 Work Continues at the Municipal Complex:  Asphalt Binder Paving and Main Power Transformer Installation! New Drone Video!

October 2017 Progress Continues at the DPW Superstructure and New Drone Video!!

September 2017 Work Progressing at the Municipal Complex DPW Superstructure

August 2017 Steel Erection for Metal Building in Progress and New Drone Video!

July 2017 Floor Placement, Building Slabs, Utility Work, Steel Delivery, and Steel Erection

May 2017 DPW work continues

April 2017 DPW foundation being poured, utility work continues

Mar. 2017 Drainage and site work continues.

Feb. 2017 Site work continues – sewer and drainage.

Jan. 2017 Winter has arrived.

Dec. 2016 Underground utilities

Nov. 2016 Groundbreaking Ceremony

Nov. 2016 Water main relocation

Oct. 2016 Filling the hole

Oct. 2016 Trees and Grass

Oct. 2016 Fire in the hole!

July – Sept. 2016 Site Prep